The Simco Road designated industrial zone recommended by Elmore P&Z cannot accommodate nuclear plant January 16, 2009

Posted by cleanidahoenergy in AEHI, approval process, economic benefits, Elmore County, Energy policy, Greenfield nuclear development, rural nuclear, Water policy.
Tags: , , , , , , , , , , , , ,
trackback

On Jan. 12, I was invited to make a presentation before the Mountain Home City Council on our efforts to develop a large advanced nuclear reactor in Elmore County.

In November, the Elmore County Planning and Zoning Commission recommended against rezoning approximately 1,400 acres of land to accommodate our plant, saying heavy industrial development should be located in a zone near Simco Road, even as wind, solar and natural gas power are permitted elsewhere in the county.

In response to a Mountain Home City Council member’s question regarding siting of the plant in the Simco Road area, the following is my reply:

After some research we have concluded the Simco Road site does not qualify for a nuclear plant and even if it did, there does not appear to be any property available. The following are some of the reasons.

The Simco Road site has no water supply so a dedicated water line of more than 20 miles would need to be constructed. A large safety-related pipeline would add hundreds of millions in expense and create security and right-of-way concerns; the Nuclear Regulatory Commission would disapprove the Simco Road site for the water supply security issue alone. Our current site is one mile from the Snake River, an ideal location for water access without a security issue.

Elmore County's proposed Simco Road industrial site is closer to Boise development than it is to Mountain Home

Elmore County's proposed Simco Road industrial site is closer to Boise development than it is to Mountain Home

The Simco Road location has geologic issues that could make qualification expensive, if it is possible at all, on account of strict NRC requirements regarding geologic stability. Preliminary geologic testing confirms our existing site has no such potential issues.

Key parcels along the Simco Road site are under option by other parties,

Our proposed location will ensure many economic benefits stay concentrated in Elmore County

Our proposed location will ensure many economic benefits stay concentrated in Elmore County

making it unavailable for a nuclear plant site. Our current proposed site is optioned and ready for the development process.

The Simco Road area is 7 miles from Boise’s industrial area and 21 miles from Mountain Home, along the Ada-Elmore county border. Elmore County would lose much of the employment revenue as employees would likely live in Boise, as suggested by our economic study. Elmore County would lose in housing starts and commercial and other economically beneficial opportunities. Our existing site is 12 miles from Mountain Home, thus in a better position of supporting economic development in Elmore County.

Elmore County’s comprehensive plan is well-intentioned, but it did not foresee the development of such a major economic benefactor like our proposed plant and the associated regulatory requirements. We look forward to our presentation before the Elmore County Commission in April for the final word on if our plant – and the economic benefits it will bring – will become possible in Elmore County.

We aren’t the only ones with this belief. One of our critics agrees the Simco Road site is lacking for our kind of development.

Advertisements

Comments»

No comments yet — be the first.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: